Construction Update – July 2024

20 CambridgeSide Place Substantially complete and ready for tenant fit out. 60 First Street Substantially complete, partially occupied and tenant fit outs ongoing. Canal Park Completion of Ramps, Stair and Handrails Installation of underground electric for new lighting. Installation of new plantings For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Construction Update – April 2024

20 CambridgeSide Place Substantially complete and ready for tenant fit out. 60 First Street Substantially complete and tenant fit out ongoing. Canal Park Installation of drainage system. Installation of underground electric for new lighting. Preparation of areas for new stairs and ramps. For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Construction Update – January 2024

20 CambridgeSide Place Substantially complete and ready for tenant fit out. 60 First Street Substantially complete and tenant fit out ongoing. Canal Park Installation of drainage system. Underground electric for new lighting. Prepare areas for new stairs and ramps. For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Construction Update – September 2023

20 CambridgeSide Place Completion of building façade. Completion of mechanical, electrical, plumbing. Completion of interior finishes. 60 First Street Completion of the building façade. Completion of interior finishes. Canal Park Mobilization and preparation work is ongoing. For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Construction Update – July 15 2023

20 CambridgeSide Place Installation of building façade ongoing Installation of mechanical, electrical, plumbing ongoing Interior finish construction ongoing As part of completing the exterior work at 20 CambridgeSide, the CambridgeSide Place parking garage entrance (next to The Cheesecake Factory) will be temporarily closed on Monday, June 12 through Friday, June 16, 2023. All traffic will be directed to the First Street parking garage entrance. CambridgeSide Place and the garage exit will remain open.  60 First Street Installation of building façade ongoing Interior finish construction ongoing Canal Park During the week of July 17, improvements work in Canal Park will begin,…

Construction Update – June 15 2023

20 CambridgeSide Place Installation of building façade ongoing Installation of mechanical, electrical, plumbing ongoing Interior finish construction ongoing As part of completing the exterior work at 20 CambridgeSide, the CambridgeSide Place parking garage entrance (next to The Cheesecake Factory) will be temporarily closed on Monday, June 12 through Friday, June 16, 2023. All traffic will be directed to the First Street parking garage entrance. CambridgeSide Place and the garage exit will remain open.  60 First Street Installation of building façade ongoing Interior finish construction ongoing For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt…

Construction Update – April 15 2023

20 CambridgeSide Place Installation of building façade ongoing Installation of mechanical, electrical, plumbing ongoing Interior finish construction ongoing 60 First Street Installation of building façade ongoing Interior finish construction ongoing For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Construction Update – March 15 2023

20 CambridgeSide Place Installation of building façade ongoing Installation of mechanical, electrical, plumbing ongoing Removal of tower crane Installation of building finishes ongoing 60 First Street Installation of building façade ongoing Installation of mechanical, electrical, plumbing ongoing For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.

Press Release – March 6 2023

Contact: Christie Kozak | Leary PR | christie@learypr.com | 978-502-5747 SmartLabs Announces Expansion of its Labs-as-a-Service Network at CambridgeSide CAMBRIDGE, MASSACHUSETTS (March 2023) – CambridgeSide (CambridgeSide.com) has announced that Boston-based Laboratory-as-a-Service (LaaS) leader, SmartLabs will open its newest location at 100 CambridgeSide. CambridgeSide is a mixed used complex owned by a partnership between New England Development and a client advised by UBS Asset Management. The new SmartLabs laboratories at 100 CambridgeSide will deliver high quality, turnkey research, development, and related manufacturing space along with best-in-class operations support for companies of varying sizes. SmartLabs offers flexible lab and office spaces that are customizable to accommodate…

Construction Update – September 15 2022

20 CambridgeSide Place Installation of building façade ongoingInstallation of mechanical, electrical, plumbing ongoing 60 First Street Installation of building façade ongoingInstallation of mechanical, electrical, plumbing ongoing For any questions regarding construction of 20 CambridgeSide or 60 First, please contact Kurt Sjostedt at 617-243-7844 or ksjostedt@nedevelopment.com.